chapter 7. Fundamentals.
|
||
All the parts of the process described in the following chapters start from the same
|
||
fundamental system engineering activities. These include defining, for the system
|
||
involved, accidents or losses, hazards, safety requirements and constraints, and the
|
||
safety control structure.
|
||
|
||
section 7.1.
|
||
Defining Accidents and Unacceptable Losses.
|
||
The first step in any safety effort involves agreeing on the types of accidents or
|
||
losses to be considered.
|
||
In general, the definition of an accident comes from the customer and occasion-
|
||
ally from the government for systems that are regulated by government agencies.
|
||
Other sources might be user groups, insurance companies, professional societies,
|
||
industry standards, and other stakeholders. If the company or group developing the
|
||
system is free to build whatever they want, then considerations of liability and the
|
||
cost of accidents will come into play.
|
||
Definitions of basic terms differ greatly among industries and engineering disci-
|
||
plines. A set of basic definitions is used in this book (see appendix A) that reflect
|
||
common usage in System Safety. An accident is defined as:
|
||
Accident: An undesired or unplanned event that results in a loss, including loss
|
||
of human life or human injury, property damage, environmental pollution,
|
||
mission loss, etc.
|
||
An accident need not involve loss of life, but it does result in some loss that is unac-
|
||
ceptable to the stakeholders. System Safety has always considered non-human
|
||
losses, but for some reason, many other approaches to safety engineering have
|
||
limited the definition of a loss to human death or injury. As an example of an
|
||
inclusive definition, a spacecraft accident might include loss of the astronauts (if
|
||
the spacecraft is manned), death or injury to support personnel or the public, non-
|
||
accomplishment of the mission, major equipment damage (such as damage to launch
|
||
|
||
|
||
facilities), environmental pollution of planets, and so on. An accident definition used
|
||
in the design of an explorer spacecraft to characterize the icy moon of a planet in
|
||
the Earth’s solar system, for example, was [151]:
|
||
A1. Humans or human assets on earth are killed or damaged.
|
||
A2. Humans or human assets off of the earth are killed or damaged.
|
||
A3. Organisms on any of the moons of the outer planet (if they exist) are killed
|
||
or mutated by biological agents of Earth origin.
|
||
Rationale: Contamination of an icy outer planet moon with biological agents
|
||
of Earth origin could have catastrophically adverse effects on any biological
|
||
agents indigenous to the icy outer planet moon.
|
||
A4. The scientific data corresponding to the mission goals is not collected.
|
||
A5. The scientific data corresponding to the mission goals is rendered unusable
|
||
(i.e., deleted or corrupted) before it can be fully investigated.
|
||
A6. Organisms of Earth origin are mistaken for organisms indigenous to any of
|
||
the moons of the outer planet in future missions to study the outer planet’s
|
||
moon.
|
||
Rationale: Contamination of a moon of an outer planet with biological
|
||
agents of Earth origin could lead to a situation in which a future mission
|
||
discovers the biological agents and falsely concludes that they are indige-
|
||
nous to the moon of the outer planet.
|
||
A7. An incident during this mission directly causes another mission to fail
|
||
to collect, return, or use the scientific data corresponding to its mission
|
||
goals.
|
||
Rationale: It is possible for this mission to interfere with the completion of
|
||
other missions through denying the other missions access to the space
|
||
exploration infrastructure (for example, overuse of limited Deep Space
|
||
Network1 (DSN) resources, causing another mission to miss its launch
|
||
window because of damage to the launch pad during this mission, etc.)
|
||
|
||
footnote. The Deep Space Network is an international network of large antennas and communication facilities
|
||
that supports interplanetary spacecraft missions and radio and radar astronomy observations for
|
||
the exploration of the solar system and the universe. The network also supports some Earth-orbiting
|
||
missions.
|
||
|
||
Prioritizing or assigning a level of severity to the identified losses may be useful
|
||
when tradeoffs among goals are required in the design process. As an example,
|
||
consider an industrial robot to service the thermal tiles on the Space Shuttle, which
|
||
|
||
|
||
is used as an example in chapter 9. The goals for the robot are (1) to inspect the
|
||
thermal tiles for damage caused during launch, reentry, and transport of a Space
|
||
Shuttle and (2) to apply waterproofing chemicals to the thermal tiles.
|
||
Level 1:
|
||
A1.1: Loss of the orbiter and crew. (e.g., inadequate thermal protection)
|
||
A1.2: Loss of life or serious injury in the processing facility.
|
||
Level 2:
|
||
A2.1: Damage to the orbiter or to objects in the processing facility that results.
|
||
in the delay of a launch or in a loss of greater than x dollars.
|
||
A2.2: Injury to humans requiring hospitalization or medical attention and
|
||
leading to long-term or permanent physical effects.
|
||
Level 3:
|
||
A3.1: Minor human injury. (does not require medical attention or requires only
|
||
minimal intervention and does not lead to long-term or permanent physical
|
||
effects)
|
||
A3.2: Damage to orbiter that does not delay launch and results in a loss of less
|
||
than x dollars.
|
||
A3.3: Damage to objects in the processing facility (both on the floor or sus-
|
||
pended) that does not result in delay of a launch or a loss of greater than x
|
||
dollars.
|
||
A3.4: Damage to the mobile robot.
|
||
Assumption: It is assumed that there is a backup plan in place for servicing
|
||
the orbiter thermal tiles in case the tile processing robot has a mechanical
|
||
failure and that the same backup measures can be used in the event the
|
||
robot is out of commission due to other reasons.
|
||
The customer may also have a safety policy that must be followed by the contractor
|
||
or those designing the thermal tile servicing robot. As an example, the following is
|
||
similar to a typical NASA safety policy:
|
||
General Safety Policy: All hazards related to human injury or damage to the
|
||
orbiter must be eliminated or mitigated by the system design. A reasonable
|
||
effort must be made to eliminate or mitigate hazards resulting at most in
|
||
damage to the robot or objects in the work area. For any hazards that cannot
|
||
be eliminated, the hazard analysis as well as the design features and develop-
|
||
ment procedures, including any tradeoff studies, must be documented and
|
||
presented to the customer for acceptance.
|
||
|
||
|
||
One (but only one) of the controls used to avoid this type of accident is an air-
|
||
borne collision avoidance system like TCAS (Traffic alert and Collision Avoidance
|
||
System), which is now required on most commercial aircraft. While the goal of TCAS
|
||
is increased safety, TCAS itself introduces new hazards associated with its use. Some
|
||
hazards that were considered during the design of TCAS are:
|
||
H1. TCAS causes or contributes to a near midair collision (NMAC), defined as
|
||
a pair of controlled aircraft violating minimum separation standards.
|
||
H2. TCAS causes or contributes to a controlled maneuver into the ground.
|
||
H3. TCAS causes or contributes to the pilot losing control over the aircraft.
|
||
H4. TCAS interferes with other safety-related aircraft systems.
|
||
H5. TCAS interferes with the ground-based Air Traffic Control system (e.g.,
|
||
transponder transmissions to the ground or radar or radio services).
|
||
H6. TCAS interferes with an ATC advisory that is safety-related (e.g., avoiding
|
||
a restricted area or adverse weather conditions).
|
||
Ground-based air traffic control also plays an important role in collision avoidance,
|
||
although it has responsibility for a larger and different set of hazards:
|
||
H1. Controlled aircraft violate minimum separation standards (NMAC).
|
||
H2. An airborne controlled aircraft enters an unsafe atmospheric region.
|
||
H3. A controlled airborne aircraft enters restricted airspace without author-
|
||
ization.
|
||
H4. A controlled airborne aircraft gets too close to a fixed obstacle other than a
|
||
safe point of touchdown on assigned runway (known as controlled flight into
|
||
terrain or CFIT).
|
||
H5. A controlled airborne aircraft and an intruder in controlled airspace violate
|
||
minimum separation.
|
||
H6. Loss of controlled flight or loss of airframe integrity.
|
||
H7. An aircraft on the ground comes too close to moving objects or collides with
|
||
stationary objects or leaves the paved area.
|
||
H8. An aircraft enters a runway for which it does not have a clearance (called
|
||
runway incursion).
|
||
Unsafe behavior (hazards) at the system level can be mapped into hazardous
|
||
behaviors at the component or subsystem level. Note, however, that the reverse
|
||
(bottom-up) process is not possible, that is, it is not possible to identify the system-
|
||
level hazards by looking only at individual component behavior. Safety is a system
|
||
property, not a component property. Consider an automated door system. One
|
||
|
||
|
||
reasonable hazard when considering the door alone is the door closing on someone.
|
||
The associated safety constraint is that the door must not close on anyone in the
|
||
doorway. This hazard is relevant if the door system is used in any environment. If
|
||
the door is in a building, another important hazard is not being able to get out of a
|
||
dangerous environment, for example, if the building is on fire. Therefore, a reason-
|
||
able design constraint would be that the door opens whenever a door open request
|
||
is received. But if the door is used on a moving train, an additional hazard must
|
||
be considered, namely, the door opening while the train is moving and between
|
||
stations. In a moving train, different safety design constraints would apply compared
|
||
to an automated door system in a building. Hazard identification is a top-down
|
||
process that must consider the encompassing system and its hazards and potential
|
||
accidents.
|
||
Let’s assume that the automated door system is part of a train control system.
|
||
The system-level train hazards related to train doors include a person being hit by
|
||
closing doors, someone falling from a moving train or from a stationary train that
|
||
is not properly aligned with a station platform, and passengers and staff being unable
|
||
to escape from a dangerous environment in the train compartment. Tracing these
|
||
system hazards into the related hazardous behavior of the automated door compo-
|
||
nent of the train results in the following hazards:
|
||
1. Door is open when the train starts.
|
||
2. Door opens while train is in motion.
|
||
3. Door opens while not properly aligned with station platform.
|
||
4. Door closes while someone is in the doorway.
|
||
5. Door that closes on an obstruction does not reopen or reopened door does
|
||
not reclose.
|
||
6. Doors cannot be opened for emergency evacuation between stations.
|
||
The designers of the train door controller would design to control these hazards.
|
||
Note that constraints 3 and 6 are conflicting, and the designers will have to reconcile
|
||
such conflicts. In general, attempts should first be made to eliminate hazards at
|
||
the system level. If they cannot be eliminated or adequately controlled at the
|
||
system level, then they must be refined into hazards to be handled by the system
|
||
components.
|
||
Unfortunately, no tools exist for identifying hazards. It takes domain expertise
|
||
and depends on subjective evaluation by those constructing the system. Chapter 13
|
||
in Safeware provides some common heuristics that may be helpful in the process.
|
||
The good news is that identifying hazards is usually not a difficult process. The later
|
||
steps in the hazard analysis process are where most of the mistakes and effort occurs.
|
||
|
||
|
||
There is also no right or wrong set of hazards, only a set that the system stake-
|
||
holders agree is important to avoid. Some government agencies have mandated the
|
||
hazards they want considered for the systems they regulate or certify. For example,
|
||
the U.S. Department of Defense requires that producers of nuclear weapons
|
||
consider four hazards:
|
||
1. Weapons involved in accident or incidents, or jettisoned weapons, produce a
|
||
nuclear yield.
|
||
2. Nuclear weapons are deliberately prearmed, armed, launched, fired, or released
|
||
without execution of emergency war orders or without being directed to do so
|
||
by a competent authority.
|
||
3. Nuclear weapons are inadvertently prearmed, armed, launched, fired, or
|
||
released.
|
||
4. Inadequate security is applied to nuclear weapons.
|
||
Sometimes user or professional associations define the hazards for the systems they
|
||
use and that they want developers to eliminate or control. In most systems, however,
|
||
the hazards to be considered are up to the developer and their customer(s).
|
||
section 7.3.
|
||
System Safety Requirements and Constraints.
|
||
After the system and component hazards have been identified, the next major goal
|
||
is to specify the system-level safety requirements and design constraints necessary
|
||
to prevent the hazards from occurring. These constraints will be used to guide the
|
||
system design and tradeoff analyses.
|
||
The system-level constraints are refined and allocated to each component during
|
||
the system engineering decomposition process. The process then iterates over the
|
||
individual components as they are refined (and perhaps further decomposed) and
|
||
as design decisions are made.
|
||
Figure 7.1 shows an example of the design constraints that might be generated
|
||
from the automated train door hazards. Again, note that the third constraint poten-
|
||
tially conflicts with the last one and the resolution of this conflict will be an impor-
|
||
tant part of the system design process. Identifying these types of conflicts early in
|
||
the design process will lead to better solutions. Choices may be more limited later
|
||
on when it may not be possible or practical to change the early decisions.
|
||
As the design process progresses and design decisions are made, the safety
|
||
requirements and constraints are further refined and expanded. For example, a
|
||
safety constraint on TCAS is that it must not interfere with the ground-based air
|
||
traffic control system. Later in the process, this constraint will be refined into more
|
||
detailed constraints on the ways this interference might occur. Examples include
|
||
|
||
|
||
constraints on TCAS design to limit interference with ground-based surveillance
|
||
radar, with distance-measuring equipment channels, and with radio services. Addi-
|
||
tional constraints include how TCAS can process and transmit information (see
|
||
chapter 10).
|
||
Figure 7.2 shows the high-level requirements and constraints for some of the air
|
||
traffic control hazards identified above. Comparing the ATC high-level constraints
|
||
with the TCAS high-level constraints (figure 7.3) is instructive. Ground-based air
|
||
traffic control has additional requirements and constraints related to aspects of the
|
||
collision problem that TCAS cannot handle alone, as well as other hazards and
|
||
potential aircraft accidents that it must control.
|
||
Some constraints on the two system components (ATC and TCAS) are closely
|
||
related, such as the requirement to provide advisories that maintain safe separation
|
||
between aircraft. This example of overlapping control raises important concerns
|
||
about potential conflicts and coordination problems that need to be resolved. As
|
||
noted in section 4.5, accidents often occur in the boundary areas between controllers
|
||
and when multiple controllers control the same process. The inadequate resolution
|
||
of the conflict between multiple controller responsibilities for aircraft separation
|
||
contributed to the collision of two aircraft over the town of Überlingen (Germany)
|
||
|
||
|
||
in July 2002 when TCAS and the ground air traffic controller provided conflicting
|
||
advisories to the pilots. Potentially conflicting responsibilities must be carefully
|
||
handled in system design and operations and identifying such conflicts are part of
|
||
the new hazard analysis technique described in chapter 8.
|
||
Hazards related to the interaction among components, for example the inter-
|
||
action between attempts by air traffic control and by TCAS to prevent collisions,
|
||
need to be handled in the safety control structure design, perhaps by mandating
|
||
how the pilot is to select between conflicting advisories. There may be considerations
|
||
in handling these hazards in the subsystem design that will impact the behavior of
|
||
multiple subsystems and therefore must be resolved at a higher level and passed to
|
||
them as constraints on their behavior.
|
||
|
||
section 7.4.
|
||
The Safety Control Structure.
|
||
The safety requirements and constraints on the physical system design shown in
|
||
section 7.3 act as input to the standard system engineering process and must be
|
||
incorporated into the physical system design and safety control structure. An
|
||
example of how they are used is provided in chapter 10.
|
||
Additional system safety requirements and constraints, including those on opera-
|
||
tions and maintenance or upgrades will be used in the design of the safety control
|
||
structure at the organizational and social system levels above the physical system.
|
||
There is no one correct safety control structure: what is practical and effective will
|
||
depend greatly on cultural and other factors. Some general principles that apply to
|
||
all safety control structures are described in chapter 13. These principles need to be
|
||
combined with specific system safety requirements and constraints for the particular
|
||
system involved to design the control structure.
|
||
The process for engineering social systems is very similar to the regular system
|
||
engineering process and starts, like any system engineering project, with identifying
|
||
system requirements and constraints. The responsibility for implementing each
|
||
requirement needs to be assigned to the components of the control structure, along
|
||
with requisite authority and accountability, as in any management system; controls
|
||
must be designed to ensure that the responsibilities can be carried out; and feedback
|
||
loops created to assist the controller in maintaining accurate process models.
|
||
|
||
section 7.4.1. The Safety Control Structure for a Technical System.
|
||
An example from the world of space exploration is used in this section, but many
|
||
of the same requirements and constraints could easily be adapted for other types
|
||
of technical system development and operations.
|
||
The requirements in this example were generated to perform a programmatic
|
||
risk assessment of a new NASA management structure called Independent
|
||
|
||
Technical Authority (ITA) recommended in the report of the Columbia Accident
|
||
Investigation Board. The risk analysis itself is described in the chapter on the new
|
||
hazard analysis technique called STPA (chapter 8). But the first step in the safety
|
||
or risk analysis is the same as for technical systems: to identify the system hazards
|
||
to be avoided, to generate a set of requirements for the new management structure,
|
||
and to design the control structure.
|
||
The new safety control structure for the NASA manned space program was
|
||
introduced to improve the flawed engineering and management decision making
|
||
leading to the Columbia loss. The hazard to be eliminated or mitigated was:
|
||
|
||
System Hazard:
|
||
Poor engineering and management decision making leading to a loss.
|
||
|
||
Four high-level system safety requirements and constraints for preventing the
|
||
hazard were identified and then refined into more specific requirements and
|
||
constraints.
|
||
1. Safety considerations must be first and foremost in technical decision
|
||
making.
|
||
a. State-of-the art safety standards and requirements for NASA missions must
|
||
be established, implemented, enforced, and maintained that protect the
|
||
astronauts, the workforce, and the public.
|
||
b. Safety-related technical decision making must be independent from pro-
|
||
grammatic considerations, including cost and schedule.
|
||
c. Safety-related decision making must be based on correct, complete, and
|
||
up-to-date information.
|
||
d. Overall (final) decision making must include transparent and explicit con-
|
||
sideration of both safety and programmatic concerns.
|
||
e. The Agency must provide for effective assessment and improvement in
|
||
safety-related decision making.
|
||
2. Safety-related technical decision making must be done by eminently qualified
|
||
experts, with broad participation of the full workforce.
|
||
a. Technical decision making must be credible (executed using credible per-
|
||
sonnel, technical requirements, and decision-making tools) .
|
||
b. Technical decision making must be clear and unambiguous with respect to
|
||
authority, responsibility, and accountability.
|
||
c. All safety-related technical decisions, before being implemented by the
|
||
Program, must have the approval of the technical decision maker assigned
|
||
responsibility for that class of decisions.
|
||
|
||
d. Mechanisms and processes must be created that allow and encourage all
|
||
employees and contractors to contribute to safety-related decision making.
|
||
3. Safety analyses must be available and used starting in the early acquisition,
|
||
requirements development, and design processes and continuing through the
|
||
system life cycle.
|
||
a. High-quality system hazard analyses must be created.
|
||
b. Personnel must have the capability to produce high-quality safety
|
||
analyses.
|
||
c. Engineers and managers must be trained to use the results of hazard analy-
|
||
ses in their decision making.
|
||
d. Adequate resources must be applied to the hazard analysis process.
|
||
e. Hazard analysis results must be communicated in a timely manner to those
|
||
who need them. A communication structure must be established that
|
||
includes contractors and allows communication downward, upward, and
|
||
sideways (e.g., among those building subsystems).
|
||
f. Hazard analyses must be elaborated (refined and extended) and updated
|
||
as the design evolves and test experience is acquired.
|
||
g. During operations, hazard logs must be maintained and used as experience
|
||
is acquired. All in-flight anomalies must be evaluated for their potential to
|
||
contribute to hazards.
|
||
4. The Agency must provide avenues for the full expression of technical con-
|
||
science (for safety-related technical concerns) and provide a process for full
|
||
and adequate resolution of technical conflicts as well as conflicts between
|
||
programmatic and technical concerns.
|
||
a. Communication channels, resolution processes, adjudication procedures
|
||
must be created to handle expressions of technical conscience.
|
||
b. Appeals channels must be established to surface complaints and concerns
|
||
about aspects of the safety-related decision making and technical conscience
|
||
structures that are not functioning appropriately.
|
||
Where do these requirements and constraints come from? Many of them are based
|
||
on fundamental safety-related development, operations and management principles
|
||
identified in various chapters of this book, particularly chapters 12 and 13. Others
|
||
are based on experience, such as the causal factors identified in the Columbia and
|
||
Challenger accident reports or other critiques of the NASA safety culture and of
|
||
NASA safety management. The requirements listed obviously reflect the advanced
|
||
technology and engineering domain of NASA and the space program that was the
|
||
focus of the ITA program along with some of the unique aspects of the NASA
|
||
|
||
|
||
culture. Other industries will have their own requirements. An example for the
|
||
pharmaceutical industry is shown in the next section of this chapter.
|
||
There is unlikely to be a universal set of requirements that holds for every safety
|
||
control structure beyond a small set of requirements too general to be very useful
|
||
in a risk analysis. Each organization needs to determine what its particular safety
|
||
goals are and the system requirements and constraints that are likely to ensure that
|
||
it reaches them.
|
||
Clearly buy-in and approval of the safety goals and requirements by the stake-
|
||
holders, such as management and the broader workforce as well as anyone oversee-
|
||
ing the group being analyzed, such as a regulatory agency, is important when
|
||
designing and analyzing a safety control structure.
|
||
Independent Technical Authority is a safety control structure used in the nuclear
|
||
Navy SUBSAFE program described in chapter 14. In this structure, safety-related
|
||
decision making is taken out of the hands of the program manager and assigned to
|
||
a Technical Authority. In the original NASA implementation, the technical authority
|
||
rested in the NASA Chief Engineer, but changes have since been made. The overall
|
||
safety control structure for the original NASA ITA is shown in figure 7.4.3
|
||
For each component of the structure, information must be determined about its
|
||
overall role, responsibilities, controls, process model requirements, coordination and
|
||
communication requirements, contextual (environmental and behavior-shaping)
|
||
factors that might bear on the component’s ability to fulfill its responsibilities, and
|
||
inputs and outputs to other components in the control structure. The responsibilities
|
||
are shown in figure 7.5. A risk analysis on ITA and the safety control structure is
|
||
described in chapter 8.
|
||
|
||
footnote. The control structure was later changed to have ITA under the control of the NASA center directors
|
||
rather than the NASA chief engineer; therefore, this control structure does not reflect the actual
|
||
implementation of ITA at NASA, but it was the design at the time of the hazard analysis described in
|
||
chapter 8.
|
||
|
||
|
||
section 7.4.2. Safety Control Structures in Social Systems.
|
||
Social system safety control structures often are not designed but evolve over time.
|
||
They can, however, be analyzed for inherent risk and redesigned or “reengineered”
|
||
to prevent accidents or to eliminate or control past causes of losses as determined
|
||
in an accident analysis.
|
||
The reengineering process starts with the definition of the hazards to be elimi-
|
||
nated or mitigated, system requirements and constraints necessary to increase safety,
|
||
and the design of the current safety-control structure. Analysis can then be used to
|
||
drive the redesign of the safety controls. But once again, just like every system that
|
||
has been described so far in this chapter, the process starts by identifying the hazards
|
||
|
||
|
||
and safety requirements and constraints derived from them. The process is illus-
|
||
trated using drug safety.
|
||
Dozens of books have been written about the problems in the pharmaceutical
|
||
industry. Everyone appears to have good intentions and are simply striving to opti-
|
||
mize their performance within the existing incentive structure. The result is that the
|
||
system has evolved to the point where each group’s individual best interests do not
|
||
necessarily add up to or are not aligned with the best interests of society as a whole.
|
||
A safety control structure exists, but does not necessarily provide adequate satisfac-
|
||
tion of the system-level goals, as opposed to the individual component goals.
|
||
This problem can be viewed as a classic system engineering problem: optimizing
|
||
each component does not necessarily add up to a system optimum. Consider the air
|
||
transportation system, as noted earlier. When each aircraft tries to optimize its path
|
||
from its departure point to its destination, the overall system throughput may not
|
||
be optimized when they all arrive in a popular hub at the same time. One goal of
|
||
the air traffic control system is to control individual aircraft movement in order to
|
||
|
||
|
||
optimize overall system throughput while trying to allow as much flexibility as pos-
|
||
sible for the individual aircraft and airlines to achieve their goals. The air traffic
|
||
control system and the rules of operation of the air transportation system resolve
|
||
conflicting goals when public safety is at stake. Each airline might want its own
|
||
aircraft to land as quickly as possible, but the air traffic controllers ensure adequate
|
||
spacing between aircraft to preserve safety margins. These same principles can be
|
||
applied to non-engineered systems.
|
||
The ultimate goal is to determine how to reengineer or redesign the overall
|
||
pharmaceutical safety control structure in a way that aligns incentives for the greater
|
||
good of society. A well-designed system would make it easier for all stakeholders
|
||
to do the right thing, both scientifically and ethically, while achieving their own goals
|
||
as much as possible. By providing the decision makers with information about ways
|
||
to achieve the overall system objectives and the tradeoffs involved, better decision
|
||
making can result.
|
||
While system engineering is applicable to pharmaceutical (and more generally
|
||
medical) safety and risk management, there are important differences from the
|
||
classic engineering problem that require changes to the traditional system safety
|
||
approaches. In most technical systems, managing risk is simpler because not doing
|
||
something (e.g., not inadvertently launching the missile) is usually safe and the
|
||
problem revolves around preventing the hazardous event (inadvertent launch): a
|
||
risk/no risk situation. The traditional engineering approach identifies and evaluates
|
||
the costs and potential effectiveness of different ways to eliminate or control the
|
||
hazards involved in the operational system. Tradeoffs require comparing the costs
|
||
of various solutions, including costs that involve reduction in desirable system func-
|
||
tions or system reliability.
|
||
The problem in pharmaceutical safety is different: there is risk in prescribing a
|
||
potentially unsafe drug, but there is also risk in not prescribing the drug (the patient
|
||
dies from their medical condition): a risk/risk situation. The risks and benefits
|
||
conflict in ways that greatly increase the complexity of decision making and the
|
||
information needed to make decisions. New, more powerful system engineering
|
||
techniques are required to deal with risk/risk decisions.
|
||
Once again, the basic goals, hazards, and safety requirements must first be identi-
|
||
fied [43].
|
||
System Goal: To provide safe and effective pharmaceuticals to enhance the long-
|
||
term health of the population.
|
||
|
||
Important loss events (accidents) we are trying to avoid are:
|
||
1. Patients get a drug treatment that negatively impacts their health.
|
||
2. Patients do not get the treatment they need.
|
||
|
||
|
||
Three system hazards can be identified that are related to these loss events:
|
||
H1: The public is exposed to an unsafe drug.
|
||
1. The drug is released with a label that does not correctly specify the condi-
|
||
tions for its safe use.
|
||
2. An approved drug is found to be unsafe and appropriate responses are
|
||
not taken (warnings, withdrawals from the market, etc.)
|
||
3. Patients are subjected to unacceptable risk during clinical trials.
|
||
H2: Drugs are taken unsafely.
|
||
1. The wrong drug is prescribed for the indication.
|
||
2. The pharmacist provides a different medication than was prescribed.
|
||
3. Drugs are taken in an unsafe combination.
|
||
4. Drugs are not taken according to directions (dosage, timing).
|
||
H3: Patients do not get an effective treatment they require.
|
||
1. Safe and effective drugs are not developed, are not approved for use, or
|
||
are withdrawn from the market.
|
||
2. Safe and effective drugs are not affordable by those who need them.
|
||
3. Unnecessary delays are introduced into development and marketing.
|
||
4. Physicians do not prescribe needed drugs or patients have no access to
|
||
those who could provide the drugs to them.
|
||
5. Patients stop taking a prescribed drug due to perceived ineffectiveness or
|
||
intolerable side effects.
|
||
From these hazards, a set of system requirements can be derived to prevent them:
|
||
1. Pharmaceutical products are developed to enhance long-term health.
|
||
a. Continuous appropriate incentives exist to develop and market needed
|
||
drugs.
|
||
b. The scientific knowledge and technology needed to develop new drugs and
|
||
optimize their use is available.
|
||
2. Drugs on the market are adequately safe and effective.
|
||
a. Drugs are subjected to effective and timely safety testing.
|
||
b. New drugs are approved by the FDA based upon a validated and reproduc-
|
||
ible decision-making process.
|
||
c. The labels attached to drugs provide correct information about safety and
|
||
efficacy.
|
||
|
||
|
||
d. Drugs are manufactured according to good manufacturing practices.
|
||
e. Marketed drugs are monitored for adverse events, side effects, and potential
|
||
negative interactions. Long-term studies after approval are conducted to
|
||
detect long-term effects and effects on subpopulations not in the original
|
||
study.
|
||
f. New information about potential safety risk is reviewed by an independent
|
||
advisory board. Marketed drugs found to be unsafe after they are approved
|
||
are removed, recalled, restricted, or appropriate risk/benefit information is
|
||
provided.
|
||
3. Patients get and use the drugs they need for good health.
|
||
a. Drug approval is not unnecessarily delayed.
|
||
b. Drugs are obtainable by patients.
|
||
c. Accurate information is available to support decision making about risks
|
||
and benefits.
|
||
d. Patients get the best intervention possible, practical, and reasonable for
|
||
their health needs.
|
||
e. Patients get drugs with the required dosage and purity.
|
||
4. Patients take the drugs in a safe and effective manner.
|
||
a. Patients get correct instructions about dosage and follow them.
|
||
b. Patients do not take unsafe combinations of drugs.
|
||
c. Patients are properly monitored by a physician while they are being treated.
|
||
d. Patients are not subjected to unacceptable risk during clinical trials.
|
||
In system engineering, the requirements may not be totally achievable in any practi-
|
||
cal design. For one thing, they may be conflicting among themselves (as was dem-
|
||
onstrated in the train door example) or with other system (non-safety) requirements
|
||
or constraints. The goal is to design a system or to evaluate and improve an existing
|
||
system that satisfies the requirements as much as possible today and to continually
|
||
improve the design over time using feedback and new scientific and engineering
|
||
advances. Tradeoffs that must be made in the design process are carefully evaluated
|
||
and considered and revisited when necessary.
|
||
Figure 7.6 shows the general pharmaceutical safety control structure in the
|
||
United States. Each component’s assigned responsibilities are those assumed in the
|
||
design of the structure. In fact, at any time, they may not be living up to these
|
||
responsibilities.
|
||
Congress provides guidance to the FDA by passing laws and providing directives,
|
||
provides any necessary legislation to ensure drug safety, ensures that the FDA has
|
||
|
||
|
||
enough funding to operate independently, provides legislative oversight on the
|
||
effectiveness of FDA activities, and holds committee hearings and investigations of
|
||
industry practices.
|
||
The FDA CDER (Center for Drug Evaluation and Research) ensures that the
|
||
prescription, generic, and over-the-counter drug products are adequately available
|
||
to the public and are safe and effective; monitors marketed drug products for
|
||
unexpected health risks; and monitors and enforces the quality of marketed drug
|
||
products. CDER staff members are responsible for selecting competent FDA advi-
|
||
sory committee members, establishing and enforcing conflict of interest rules, and
|
||
providing researchers with access to accurate and useful adverse event reports.
|
||
There are three major components within CDER. The Office of New Drugs
|
||
(OND) is in charge of approving new drugs, setting drug labels and, when required,
|
||
recalling drugs. More specifically, OND is responsible to:
|
||
1.•Oversee all U.S. human trials and development programs for investigational
|
||
medical products to ensure safety of participants in clinical trials and provide
|
||
oversight of the Institutional Review Boards (IRBs) that actually perform these
|
||
functions for the FDA.
|
||
2.•Set the requirements and process for the approval of new drugs.
|
||
3.•Critically examine a sponsor’s claim that a drug is safe for intended use (New
|
||
Drug Application Safety Review). Impartially evaluate new drugs for safety
|
||
and efficacy and approve them for sale if deemed appropriate.
|
||
4.•Upon approval, set the label for the drug.
|
||
5.•Not unnecessarily delay drugs that may have a beneficial effect.
|
||
6.•Require Phase IV (after-market) safety testing if there is a potential for long-
|
||
term safety risk.
|
||
7.•Remove a drug from the market if new evidence shows that the risks outweigh
|
||
the benefits.
|
||
8.•Update the label information when new information about drug safety is
|
||
discovered.
|
||
The second office within the FDA CDER is the Division of Drug Marketing, Adver-
|
||
tising, and Communications (DDMAC). This group provides oversight of the mar-
|
||
keting and promotion of drugs. It reviews advertisements for accuracy and balance.
|
||
The third component of the FDA CDER is the Office of Surveillance and Epi-
|
||
demiology. This group is responsible for ongoing reviews of product safety, efficacy,
|
||
and quality. It accomplishes this goal by performing statistical analysis of adverse
|
||
event data it receives to determine whether there is a safety problem. This office
|
||
reassesses risks based on new data learned after a drug is marketed and recommends
|
||
|
||
|
||
ways to manage risk. Its staff members may also serve as consultants to OND with
|
||
regard to drug safety issues. While they can recommend that a drug be removed
|
||
from the market if new evidence shows significant risks, only OND can actually
|
||
require that it be removed.
|
||
The FDA performs its duties with input from FDA Advisory Boards. These
|
||
boards are made up of academic researchers whose responsibility is to provide
|
||
independent advice and recommendations that are in the best interest of the general
|
||
public. They must disclose any conflicts of interest related to subjects on which
|
||
advice is being given.
|
||
Research scientists and centers are responsible for providing independent and
|
||
objective research on a drug’s safety, efficacy, and new uses and give their unbiased
|
||
expert opinion when it is requested by the FDA. They should disclose all their con-
|
||
flicts of interest when publishing and take credit only for papers on which they have
|
||
significantly contributed.
|
||
Scientific journals are responsible for publishing articles of high scientific quality
|
||
and provide accurate and balanced information to doctors.
|
||
Payers and insurers pay the medical costs for the people insured as needed
|
||
and only reimburse for drugs that are safe and effective. They control the use of
|
||
drugs by providing formularies or lists of approved drugs for which they will reim-
|
||
burse claims.
|
||
Pharmaceutical developers and manufacturers also have responsibilities within
|
||
the drug safety control structure. They must ensure that patients are protected from
|
||
avoidable risks by providing safe and effective drugs, testing drugs for effectiveness,
|
||
properly labeling their drugs, protecting patients during clinical trials by properly
|
||
monitoring the trial, not promoting unsafe use of their drugs, removing a drug from
|
||
the market if it is no longer considered safe, and manufacturing their drugs accord-
|
||
ing to good manufacturing practice. They are also responsible for monitoring drugs
|
||
for safety by running long-term, post-approval studies as required by the FDA;
|
||
running new trials to test for potential hazards; and providing, maintaining, and
|
||
incentivizing adverse-event reporting channels.
|
||
Pharmaceutical companies must also give accurate and up-to-date information
|
||
to doctors and the FDA about drug safety by educating doctors, providing all avail-
|
||
able information about the safety of the drug to the FDA, and informing the FDA
|
||
of potential new safety issues in a timely manner. Pharmaceutical companies also
|
||
sponsor research for the development of new drugs and treatments.
|
||
Last, but not least, are the physicians and patients. Physicians have the responsi-
|
||
bility to:
|
||
1.•
|
||
Make treatment decisions based on the best interests of their clients.
|
||
2.• Weigh the risks of treatment and non-treatment.
|
||
|
||
|
||
3.•Prescribe drugs according to the limitations on the label
|
||
4.•Maintain up-to-date knowledge of the risk/benefit profile of the drugs they are
|
||
prescribing
|
||
5.•Monitor the symptoms of their patients under treatment for adverse events
|
||
and negative interactions
|
||
6.•Report adverse events potentially linked to the use of the drugs they
|
||
prescribe
|
||
Patients are taking increasing responsibility for their own health in today’s world,
|
||
limited by what is practical. Traditionally they have been responsible to follow their
|
||
physician’s instructions and take drugs as prescribed, accede to the doctor’s superior
|
||
knowledge when appropriate, and go through physicians or appropriate channels to
|
||
get prescription drugs.
|
||
As designed, this safety control structure looks strong and potentially effective.
|
||
Unfortunately, it has not always worked the way it was supposed to work and the
|
||
individual components have not always satisfied their responsibilities. Chapter 8
|
||
describes the use of the new hazard analysis technique, STPA, as well as other basic
|
||
STAMP concepts in analyzing the potential risks in this structure. |